New construction of a solar power plant to provide an alternative power source for the own needs of the Horodok City Multidisciplinary Hospital
New construction of a solar power plant to provide an alternative power source for the own needs of the Horodok City Multidisciplinary Hospital
Total project budget
7 943 677 UAH
Project goal: The goal of the project is to ensure uninterrupted, reliable and environmentally friendly electricity supply to the KNP "Horodok City Multidisciplinary Hospital" by building a 150 kW solar power plant for the hospital's own needs.
The main objectives of the project are:
creating a backup alternative source of electricity for a critically important medical facility;
reducing dependence on centralized power sources, especially in conditions of energy risks, accidents or emergencies;
reducing the hospital's electricity costs;
reducing greenhouse gas emissions and increasing the energy efficiency of the community's healthcare system.
The goal is to be achieved through the implementation of a new construction of a photovoltaic power plant (PVS) on a land plot of 3.4153 hectares at the address: Horodok city, st. Shevchenko, 40.
The project involves the installation of 264 Longi 565 Wp photovoltaic modules and SUN-50K-SG01HP3-EU-BM4 hybrid inverters, providing an annual electricity generation of about 239.6 thousand kWh.
The generated energy will be fully used to meet the needs of the hospital with the possibility of connecting storage systems.
The implementation of the project will allow:
to ensure the hospital's energy independence;
to stabilize the operation of medical equipment even in the event of power outages;
to promote the community's transition to green energy and achieve sustainable development goals.